Flower Mound's planned performing arts center at the River Walk development is moving forward without a bond election, funded instead by a tax district expected to generate an estimated $50 million.

The Town Council gave staff feedback at a July 20 work session not to place the project on a November 2026 bond ballot, according to the town's arts center project page. The project is funded through Tax Increment Reinvestment Zone No. 1 (TIRZ #1), which the council voted to extend for five additional years at a Nov. 18, 2024, meeting.

The final cost will depend on the design, but the town said it expects the project to be fully covered by TIRZ #1.

The town's project page listed a Nov. 19 work session to discuss funding approaches and next steps. No recap of that session was available as of publication.

What the center could include

The facility would sit on 3.67 acres of town-owned land at 4200 River Walk Drive. It could feature a main stage theater, flexible performance spaces, multipurpose rooms, classrooms, a gallery and exhibition space for rotating shows. Outdoor spaces would connect to the River Walk trail system and neighboring restaurants and retail, according to the town.

The roots go back to 2018. A Cultural Arts Master Plan that year recommended exploring a cultural arts center. The town hired Webb Management Services in October 2019 to study potential usage and costs. After rejecting a site at 1800 Timber Creek Road in 2022 due to site constraints, the council directed staff to find land in a mixed-use setting.

The town contracted OWT Architects in March 2024 to study the River Walk site. That September, Flower Mound purchased the 3.67-acre parcel from the River Walk developers.

How it's funded

TIRZ #1 was established in September 2005 to fund public infrastructure along the FM 2499 corridor. The zone covers about 1,465 acres. Tax revenues collected above the base value set in 2005 go toward improvement projects. Denton County approved the amended TIRZ agreement in December 2024.

Timeline ahead

Hoefer Welker + BORA Architects, selected in June 2025 after a review of 28 firm qualifications, is leading the design. The predesign phase is expected to last 15 weeks and includes visioning and goal setting, space programming, conceptual design, benchmarking tours, community engagement and site plan/master plan work.

After predesign, the town's timeline lists 12 weeks for schematic design, 16 weeks for design development, 18 weeks for construction documents, nine weeks for permitting and six weeks for bid negotiation. Construction is estimated at 24 months, with a target grand opening in spring 2029.